Street lighting LED trial

Recent advances in Light Emitting Diodes (LED) technology have seen an increase in available opportunities within the street lighting industry. With increased efficiency and life expectancy, LED's are seen as the way forward to help reduce maintenance costs, energy consumption and carbon emissions.

The purpose of this trial is to review the new technology that has become available and determine whether or not it is time to consider it as a viable alternative to conventional lighting methods.

The trial will involve replacing the existing street lights on a ‘one for one’ basis at the following locations within Aylesbury.

  • Tiverton Crescent, Quarrendon.
  • Mowbray Road, Elmhurst.
  • Kings Road, Queens Park.
  • Herston Close and Corfe Close, Bedgrove.

These four locations have been chosen primarily for the following reasons:

 

  • Equipment and type of columns (concrete), which as a result of their age are due for replacement.
  • Mix of residential streets (cul-de-sac/through road).
  • Mix of communities.
  • Mix of type and age of housing.
  • Mix of electoral divisions.

The trial will run for three months from September to November and over this period other lighting options will also be trialled. The table below details these options and when they will be in use. Once the trial is over, the lighting will operate as it did before the trial started. This will be reviewed once feedback from the trial has been analysed.   

 

 Lighting Option

Date

Normal operational hours (dusk to dawn)

September 2010

Reduced lighting levels ‘dimming’

(midnight &  5.30am)

October 2010

Part-night lighting (midnight & 5.30am)

November 2010

Normal operational hours (dusk to dawn)

December 2010 onwards

 

In May site surveys were carried out and since then Transport for Buckinghamshire have been working closely with each of the manufacturers and other key partners to ensure the trial is started on time and disruption to residents is kept to a minimum. 

To ensure residents are kept fully informed, the table below details key activities that are due to take place between now and the end of February 2011.

 

Activity

Date

Delivery of update letter and ‘opinion’ survey to residents and other key stakeholders

Week commencing 26 July 2010

Installation of replacement street lights

Week commencing 2 August 2010

Transfer of electricity supplies to new street lights

Week commencing 16 August 2010

Removal of existing street lights

Week commencing 23 August 2010

Installation of new LED lanterns

Week commencing 31 August 2010

Convert lantern to dimmed setting

Week commencing 11 October 2010

Convert lantern to part-night setting

Week commencing 8 November 2010

Convert lantern back to normal operation

Week commencing 6 December 2010

Delivery of ‘consultation’ survey to residents and other key stakeholders

Week commencing 13 December 2010

Results of trial to be forwarded to residents and other key stakeholders

Week commencing 28 February 2011

 

To help determine the outcome of the trial, Transport for Buckinghamshire is seeking support from residents and other key stakeholders by asking them to complete before and after surveys. The first survey was delivered to residents in July and was seeking their opinion with regards the existing lighting in their street as well as their current views on the three lighting options listed above. A further survey will be delivered to residents in December. Surveys can be completed electronically by visiting our have you say page.